Feb 25, 2008

Boren Avenue / Madison Street paving projects

See: http://www.seattle.gov/transportation/boren_madison_pave.htm

Project Location

• Boren Avenue from Broadway to Denny Way
• Madison Street from Terry Avenue to 18th Avenue E

Schedule

• Paving: April 2008 through October 2008
• Street trees and spot sidewalk repairs: During 2008 and 2009

What to Expect During Construction

• Lane closures during off-peak hours
• Pedestrian detours
• Parking restrictions
• Moderate construction noise and dust
• Normal work hours will be 7 am – 4 pm, with occasional night time and weekend work
• SDOT will distribute regular notices with more location specific information during construction

Project Contacts
• George Frost, Public Outreach Coordinator, george.frost@seattle.gov, (206) 615-0786
• Jessica Murphy, Project Manager, jessica.murphy@seattle.gov, (206) 684-0178