Madison Street Paving Project starts April 28th
 The overall project work will be done in four (4) phases described below, with some overlap between each phase:
The overall project work will be done in four (4) phases described below, with some overlap between each phase:
1.    Madison Street from 10th Avenue to 18th  Avenue E  (late April - mid June)
2.    Madison from Terry Avenue to 10th  Avenue (late May - mid July)
3.    Boren Avenue from Broadway to Seneca Street  (late June - late August)
4.    Boren Avenue from Seneca Street to Denny Way  (late July - mid October)
The work in each phase will roughly follow this order:  (1) pavement base repairs and curbs/sidewalks; (2) pavement grinding; (3) drainage grates and manhole adjustments; (4) lighting and traffic signal detector installations; (5) final paving and pavement striping.
Pavement grinding and final paving will happen during the night and/or on a
weekend.
What to Expect During Construction
•    Lane closures
•    Pedestrian detours
•    Parking restrictions
•    Moderate construction noise and dust
•    Normal work hours will be 7 a.m. - 4 p.m., with occasional night time and weekend work
•    Regular notices with more location specific information during construction
For More Information
Please visit SDOT’s website at:
http://www.seattle.gov/transportation/boren_madison_pave.htm
 to view information updates or to sign up to receive email news on project status.
Project Contacts
George Frost, Public Outreach Coordinator, george.frost@seattle.gov, (206) 615-0786
Jessica Murphy, Project Manager, jessica.murphy@seattle.gov, (206) 684-0178
 