Madison Street Paving Project starts April 28th

The overall project work will be done in four (4) phases described below, with some overlap between each phase:

1. Madison Street from 10th Avenue to 18th Avenue E (late April - mid June)
2. Madison from Terry Avenue to 10th Avenue (late May - mid July)
3. Boren Avenue from Broadway to Seneca Street (late June - late August)
4. Boren Avenue from Seneca Street to Denny Way (late July - mid October)

The work in each phase will roughly follow this order: (1) pavement base repairs and curbs/sidewalks; (2) pavement grinding; (3) drainage grates and manhole adjustments; (4) lighting and traffic signal detector installations; (5) final paving and pavement striping.

Pavement grinding and final paving will happen during the night and/or on a
weekend.

What to Expect During Construction
• Lane closures
• Pedestrian detours
• Parking restrictions
• Moderate construction noise and dust
• Normal work hours will be 7 a.m. - 4 p.m., with occasional night time and weekend work
• Regular notices with more location specific information during construction

For More Information
Please visit SDOT’s website at:
http://www.seattle.gov/transportation/boren_madison_pave.htm
to view information updates or to sign up to receive email news on project status.

Project Contacts
George Frost, Public Outreach Coordinator, george.frost@seattle.gov, (206) 615-0786
Jessica Murphy, Project Manager, jessica.murphy@seattle.gov, (206) 684-0178

No comments: